Step by Step Guide to Creating a Preliminary Estimate:

A preliminary estimate sets the financial direction for any construction project. It is the first realistic number owners, designers, and lenders see, so it must be clear, documented, and defensible. A high-quality preliminary estimate helps decide whether to proceed, where to value-engineer, and how much contingency to hold. Professionals often combine experience, benchmark data, and tools to produce these early budgets; many rely on preliminary estimating services to gather accurate unit rates, regional adjustments, and reporting templates. This guide walks you through each step required to create a reliable preliminary construction estimate, with practical tips, common pitfalls, and a worked example you can reuse.

Who should prepare a preliminary estimate

Quantity surveyors, cost estimators, cost engineers, or experienced project managers typically prepare preliminary estimates. If you are an owner, developer, or designer preparing your own estimate, this guide gives you the professional steps to follow and the checks to include.

Overview: common estimating methods

Unit rate (cost per square foot or meter), elemental (cost by building elements such as foundation, superstructure, finishes), parametric (using coefficients like cost per bed for hospitals), and assembly or systems-based estimating are the most common methods. Choice of method depends on the project stage and available information.

Step 1: Clarify project objectives and constraints

Write a short scope statement describing the project purpose, expected capacity, quality level, approximate floor area, and key constraints such as budget limit, delivery time, or sustainability targets. Example checklist items:

  • Project type (residential, commercial, industrial)
  • Expected floor area or number of units
  • Quality level (basic, standard, premium)
  • Target completion date or phasing requirements
  • Known constraints (site access, protected trees, local bylaws)

Tip: Put assumptions in a single list that you will attach to the estimate for transparency.

Step 2: Gather available documents and data

Collect everything that informs cost: concept sketches, preliminary layouts, site plan, geotechnical reports (if available), utility maps, similar-project cost records, and client requirements. If documents are limited, note the degree of uncertainty in your assumptions.

Step 3: Do a basic site assessment (desktop or physical)

Identify obvious site cost drivers: slope, access roads, contamination history, rock excavation potential, and space for laydown. If you can, obtain a report or at least a site visit note. Site constraints often change foundations, drainage, temporary works, and logistics costs.

Step 4: Select the estimating method appropriate to stage and data

If you only know floor area, use a unit-rate or parametric method. If you have schematic layouts, use elemental or approximate quantity takeoff. If you have BIM or detailed drawings, you can progress toward a detailed estimate. Choose the simplest method that reasonably reflects the available information.

Step 5: Define the estimating breakdown (work breakdown structure)

Create a clear structure for the estimate so it is easy to review and update. A typical breakdown is:

  • Preliminary summary (total)
  • Direct construction costs by element (substructure, superstructure, finishes, services)
  • External works and landscaping
  • Temporary works and site establishment
  • Indirect costs (site overheads and general overheads)
  • Contingency and escalation
  • Professional fees and permits
  • Contractor profit

Use consistent headings and numbering so reviewers can reference items easily.

Step 6: Prepare unit rates or assembly rates

Assemble unit rates per material or assembly from reliable sources: recent local projects, cost databases, supplier quotes, or published price books. Document the source and date for each rate so it can be updated later. Typical rate sources include local contractors, suppliers, regional cost databases, and previous project records.

Tip: If you find a rate in a foreign currency, convert it using current exchange and then adjust for local productivity.

Step 7: Do an approximate quantity takeoff

Measure quantities from the available drawings or use benchmark ratios if drawings are not available. Examples: floor area, external wall area, roof area, linear meters of foundations. For each measured item multiply by its unit rate.

Worked example (elemental unit approach)
Assume a small building with gross floor area 150 square meters and the following elemental rates per square meter: structure 300, finishes 200, services 80, external works 60. Calculate the direct construction cost.

Step-by-step arithmetic:
Calculate total rate per square meter:
300 + 200 + 80 + 60 = 640 per m2.

Multiply by area:
150 times 640.

Compute 150 × 640 by digit steps:
150 × 640 = 150 × (600 + 40)
150 × 600 = 90,000
150 × 40 = 6,000
Sum = 90,000 + 6,000 = 96,000

Direct construction cost = 96,000 (currency units)

Step 8: Add indirect costs (site overheads and general overheads)

Indirect costs cover site setup, temporary utilities, security, project management, and head office overhead allocation. Choose percentages based on project scale and market practice or estimate as itemized values. Example: apply 12% for indirects.

Compute indirects for the example:
Indirects = 96,000 × 12 percent.

Digit steps:
12 percent means 12/100 = 0.12.
96,000 × 0.12 = (96,000 ÷ 100) × 12
96,000 ÷ 100 = 960
960 × 12 = (960 × 10) + (960 × 2) = 9,600 + 1,920 = 11,520

Subtotal after indirects:
96,000 + 11,520 = 107,520

Step 9: Apply contingency and escalation (inflation)

Contingency covers scope uncertainty and known unknowns. Escalation accounts for price increases between estimate and construction. Typical contingency at preliminary stage is 5 to 15 percent depending on design maturity and risk.

Apply 10 percent contingency to subtotal in the example:
Contingency = 107,520 × 10 percent.

Digit steps:
10 percent = 10/100 = 0.10
107,520 × 0.10 = 10,752

Subtotal after contingency:
107,520 + 10,752 = 118,272

If escalation is expected between now and start (for example 3 percent per year), calculate escalation separately and add or present it as a future-cost scenario.

Step 10: Add professional fees, permits, and statutory charges

Include architects, engineers, surveyors, testing, and permit fees. This is often expressed as a percentage of construction cost or as lump sums. Example: professional fees 5 percent.

Compute professional fees on subtotal:
Professional fees = 118,272 × 5 percent.

Digit steps:
5 percent = 5/100 = 0.05
118,272 × 0.05 = (118,272 ÷ 100) × 5
118,272 ÷ 100 = 1,182.72
1,182.72 × 5 = 1,182.72 × (4 + 1) = (1,182.72 × 4) + 1,182.72
1,182.72 × 4 = 4,730.88
4,730.88 + 1,182.72 = 5,913.60

Add to subtotal:
118,272 + 5,913.60 = 124,185.60

Round as needed:
Rounded total before profit = 124,186 (rounded to nearest whole currency unit)

Step 11: Add contractor profit and finalize the estimate

Contractor profit margin varies with market and risk. Typical preliminary margins range from 5 to 12 percent. Apply chosen margin and present the final figure.

Example with 7 percent profit on rounded subtotal 124,186:
Profit = 124,186 × 7 percent.

Digit steps:
7 percent = 7/100 = 0.07
124,186 × 0.07 = (124,186 ÷ 100) × 7
124,186 ÷ 100 = 1,241.86
1,241.86 × 7 = (1,241.86 × 5) + (1,241.86 × 2)
1,241.86 × 5 = 6,209.30
1,241.86 × 2 = 2,483.72
Sum = 6,209.30 + 2,483.72 = 8,693.02

Final estimate:
124,186 + 8,693.02 = 132,879.02
Round to nearest whole:
Final preliminary estimate = 132,879

Document the rounding rules you used and whether final numbers are net of tax or inclusive of tax.

Step 12: Validate with benchmarking and sensitivity analysis

Cross-check your result against benchmark cost per square meter for similar projects and run sensitivity tests for main drivers (material price +10 percent, labor +10 percent, contingency changes). For each scenario recalculate totals and present the range.

Quick sensitivity example: material cost up 10 percent. If direct cost includes materials that represent 50 percent of direct cost, approximate increase is 0.50 × 10 percent = 5 percent on direct cost. Recalculate direct cost and repeat the indirects and margins to show the impact.

Step 13: Document assumptions, exclusions, and level of accuracy

List assumptions such as productivity rates, site access, foundation type, unit rates used, currency and date of rates, and excluded items. State the expected accuracy range (for example plus/minus 15 percent) based on the estimate method and available data.

Step 14: Prepare the estimate report and presentation

Create a clear summary page with: project description, total preliminary estimate, key assumptions, risk register, contingency policy, and a short explanation of methodology. Include a detailed line item appendix and rate sources so reviewers can audit or update the estimate later.

Common pitfalls and how to avoid them

  • Using outdated rates without adjustment. Always record the date of each source and apply escalation indexes.
  • Forgetting temporary works, testing, or site mobilization. Use a standard checklist for indirects.
  • Under-allocating contingency. Choose contingency based on risk register, not optimism.
  • Not documenting assumptions. Unclear assumptions cause disputes and rework.
  • Treating the preliminary estimate as a tender price. Make sure users know the accuracy band and required next steps to refine it.

Practical tips to improve preliminary estimate accuracy

  • Involve a cost professional early to reduce bias.
  • Use local recent projects as benchmarks rather than distant data.
  • Keep a “live” cost database and update it quarterly.
  • Use simple spreadsheets with clear links from quantities to rates to totals.
  • Include a short sensitivity table in the summary (low, base, high scenarios).

When to revise the preliminary estimate

Revise when scope changes, major design decisions are made, market conditions change significantly, new site information becomes available, or when moving from schematic to detailed design. Each revision should be versioned and dated.

Conclusion

A good preliminary estimate is systematic, transparent, and documented. Follow the steps in this guide: clarify objectives, gather data, choose an appropriate method, measure quantities, apply validated rates, add indirects and contingencies, and validate with benchmarks and sensitivity tests. Clear documentation of assumptions and a robust risk-driven contingency will make your preliminary estimate useful for decision-making and reduce the chance of unpleasant budget surprises later.

FAQs

Q1. How accurate is a preliminary estimate?
Accuracy depends on available information and method used. Early conceptual estimates may vary by -30 percent to +50 percent, while estimates produced at schematic design typically fall in -15 percent to +30 percent. State the expected accuracy with the estimate.

Q2. How much contingency should I include?
Contingency is project-specific. At preliminary stage typical ranges are 5 to 15 percent. Use higher contingency for higher uncertainty or complex projects.

Q3. Should I include escalation in the preliminary estimate?
Yes, if construction will start in the future and market inflation is likely. Present escalation as a separate line or as scenarios.

Q4. Can I rely on a unit-rate per square meter only?
Unit rates per square meter give a fast order-of-magnitude but can hide element-specific risks. If possible, combine unit rates with elemental checks for critical items.

Q5. How often should cost rates be updated?
Update rates at least quarterly in volatile markets and before preparing any estimate. Always record the date source for audit.

Q6. Who should approve the assumptions used in the estimate?
Key stakeholders such as the owner, project manager, and lead designer should review and sign off assumptions to avoid misunderstandings.